ALTON PLANNING BOARD
Tuesday, May 21, 2019, at 6:00 p.m.
ALTON TOWN HALL
AGENDA
Call to Order
Approval of Agenda

1. Continued from April 16, 2019
Case # P19-01
Thomas W. Varney, P.E., of Varney Engineering, LLC, Agent for Keith Babb of Green Oak Realty, Owner
Map 5 Lot 72, Conceptual Consultation
Rural (RU) Zone, Suncook Valley Road

Proposal: To expand the existing excavation.

2. Administrative Review for Completion
Case #P06-93
John Jeddrey, Trustee, Jeddrey Realty Trust, Owner
Map 15 Lots 56-3, 56-4, 56-21, 56-23, 57, & 60-5 through -20
Final Major Subdivision-Administrative Review for Completion
Rural (RU) Zone, Old Wolfeboro Road and NH Route 28

Proposal: Applicant asked what was needed to start work again and complete the subdivision.

3. Completeness Review of Application and Public Hearing if Application is Accepted as Complete
Case #P19-10
Jones Family Rev. Trust, Rhona B. Jones, Trustee, Owner
Map 15 Lot 80, Final Minor Site Plan
Rural (RU) Zone, 355 Drew Hill Road

Proposal: To convert an existing workshop into a “Second Hand Shop”, with no plans to change the property, and no proposed new construction.

Case # P19-11
One80 Solar Group, LLC, Agent for David R. Hussey, Owner
Map 5 Lot 72-7, Final Major Site Plan
Rural (RU) Zone, 356 Suncook Valley Road

Proposal: To construct and install an approximately 3 megawatt AC (4 megawatt DC) photovoltaic power station, in three separate solar array sections within the subject parcel.

Other Business:
1. Old Business:
a. Continued discussion regarding Construction Observation Guidelines.

2. New Business:

3. Approval of Minutes: April 16, 2019

4. Correspondence for the Board's review/discussion/action:
a. Email correspondence regarding Right Field Development’s detention pond and as-built plan, dated April 17, April 18, and April 19, 2019, between Richard D’Angelo, Mike Vignale, P.E., and Nic Strong.
b. Letters dated April 19, 2019, from John Dever, III, Code Official, re: Notices of Violation for the Williams and Coffin Brook Gravel Pit.
c. Letters dated April 18, 2019, from the Alton Board of Selectmen, re: Notices of Intent to Excavate for the Williams and Coffin Brook Gravel Pit.
d. Letter dated May 8, 2019, from the Alton Conservation Commission, re: the permission from the Conservation Board to be within 10 feet of the property line.
e. Letter dated May 15, 2019, from Eckman Engineering, LLC, re: Scott & Penny Williams’ conditions of approval for their gravel pit.

5. Correspondence for the Board's information:
a. Letter dated May 14, 2019, from NH DOT, re: the reinstallation of rumble strips following resurfacing NH Routes 11 and 28 in Alton.

6. Any Other Business that may come before the Board:

Public Input on Non-Case Specific Local Planning Issues

Adjournment

Roger Sample, Planning Board Chairman

NS/jac

5/10/2019
Revised 5/17/2019 and 5/21/2019

Back to Top